Fabiano Abel Fernandes judge ordered the stoppage of works of the project Nexus Shopping & amp; Business, located in the Marist Sector, in Goiânia.
The magistrate accepted request made in a lawsuit filed by the Public Ministry of Goiás. The accuser agency acted after councilor Djalma Araújo (NETWORK Sustainability) report numerous irregularities in the work.
With the decision are also suspended the effects of the license for the construction that were granted by the Goiânia City Hall.
As residents and people that travel close to the project, the traffic already is bad without a building of this magnitude. With the Nexus the situation will get even worse. The forecast is to triple the delay to cross the avenue 85 after the project work.
The decision requires companies aware JFG Incorporations SPE 001 Ltda., Conscious Construction and Incorporated Ltda., And JFG Construcoes e Participacoes Ltda. to present to the city of Goiânia new Neighborhood Impact Study (EIV) and Traffic Impact Study (EIT).
“They can show what they want. A work that size has no condition to be in that place. Its onset is severe: it shows that sharks dominate the city and that she has to submit to the great entrepreneurs, who act as kings of Goiania, “says Djalma Araújo
With the new order, the IVE should. understand a new survey with residents.
Djalma reported that the interviews were jorjadas. And comprobar himself made other that no respondent defended the project, which can catch the transit of Goiânia.
The Justice wants interviews that clearly show the names of the respondents, the location of the interview and your documents personal. The court will ask for further investigation of the interviews.
several polls of the press were made on site and most are said against the project.
After the meeting several documents, says judge the Prefeiturade Goiânia should inform the public and call it to popular participation and decide what will be done on site.
Fine daily 5000 for the decision failure
in the event of default as the halt in construction and suspension of the license for
in April this year the Julian Araújo prosecutor proposed environmental civil action to prohibit, first, the start of the construction work until the final judgment of the action, which is being processed the 2nd Court of Public Finance Municipal. In action, he argued that, in October last year, the MP began to investigate news of irregularities in the administrative procedure for examination and approval of the Nexus building project, which is located in the Avenues D and 85 and 143-A, Sector . Marist
for him, one should add to the magnitude of the enterprise to its location: the confluence of important avenues, junction two structuring road corridors that are part of the basic road macrorrede, formed by the arterial roads of 1st category as defined in the Director of the Capital Plan. It adds be historical chaotic situation of urban mobility in the region that even with the installation of a trench passage, failed to solve the daily traffic jams on site, being the Avenue 85 classified as one of the ten worst points of Goiania jams. (MP Advisory)
.
No comments:
Post a Comment